• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
  • Skip to secondary sidebar

The Lincoln Squirrel – News, features and photos from Lincoln, Mass.

  • Home
  • About/Contact
  • Advertise
  • Legal Notices
    • Submitting legal notices
  • Lincoln Resources
    • Coming Up in Lincoln
    • Municipal Calendar
    • Lincoln Links
  • Merchandise
  • Subscriptions
    • My Account
    • Log In
    • Log Out
  • Lincoln Review
    • About the Lincoln Review
    • Issues
    • Submit your work

school project*

School project budget, financing aired at SOTT

October 21, 2018

A summary of “value engineering” items trimmed to bring the school project back to the approved $93.9 budget (click to enlarge).

Town officials provided updates on the two pending school campus construction projects at the State of the Town meeting on October 20, outlining a series of cuts made to bring the school project under budget and a timeline for the community center.

The detailed construction cost estimate presented to the School Building Committee in September was about $9 million more than the $93.9 million budget approved by voters in June, so the SBC had just weeks to decide what to trim as it prepares for bonding votes at a Special Town Meeting on December 1 and at the ballot box on December 3. The areas where cost estimates rose the most compared to the figures presented in June were site work, which went up by $5.22 million, and temporary modular classrooms, which rose by $2.94 million.

After three weeks of painstakingly combing through a list of more than 100 construction items, the SBC got the project under budget. Members actually trimmed more than $9 million because they also added two items: $870,000 for an upgraded HVAC system and $150,000 for a slightly redesigned center of the building.

The biggest savings will come from site work. The SBC lopped $3.9 million from that category by cutting back on granite curbs and repaving and foregoing new plantings, sod for the ballfield, and new playground equipment. Officials expect to save $1.68 million by negotiating less expensive temporary classrooms.

To save another $2.5 million, the town will hire a third-party firm to install the solar equipment rather than paying for and owning it as part of the project. Lincoln would then enter into a power purchase agreement where it would buy electricity, thus shifting much of the financial burden from the construction budget to the operating budget. On the bright side, this also means that enough solar equipment can be installed to make the school “net zero” in terms of energy use.

The final borrowing amount that the town will vote on in December hasn’t been determined yet, because other sources of funding have to be nailed down. Those sources include the following (with current balances in parentheses):

  • The debt stabilization fund ($5.5 million). This fund has been accumulating for years in anticipation of the school project, though the Finance Committee may recommend retaining some of it for the Community Center project
  • Free cash (about $1 million). This is a relatively large amount because the town recently received a large building permit fee.
  • Community Preservation Act funds (about $600,000 not otherwise designated). These funds can be used to outdoor recreational things like athletic fields and playgrounds.
  • The cable revolving fund ($226,000) from the annual license fee to support local cable access. This fund balance increases by about $80,000 a year and Town Administrator Tim Higgins will recommend that the Board of Selectmen “commit the lion’s share of that money” to applicable parts of the school project such as audiovisual work in the Brooks auditorium, he said at an October 18 multiboard meeting.

The town considered using Chapter 90 state funds for roadway improvements to Ballfield Road as part of the school project but decided it would be unwise to divert that money from regular road maintenance around town.

  • Click here for the State of the Town presentations by the School Building Committee and Finance Committee

Estimated property tax increases as a result of the school borrowing (click to enlarge).

The precise tax impacts of the borrowing won’t be known until the final borrowing amount and bond interest rate are known. “It’ll be less than the 20 percent people had in their minds due to the tranching, but it won’t be a lot less,” Finance Committee chair Jim Hutchinson said. “Tranching” means splitting up the borrowing into two or more loans over a period of time rather than borrowing the full amount in a single loan. Earlier FinCom figures indicated tax increases of 19 to 21 percent. The median tax bill in fiscal 2018 was $13,566.

The town also expects to borrow roughly another $20 million in 2024 to build the community center, which will bring the town’s debt service levels back up to 2019 levels. The most recent estimates for that project range from $15.3 million to $16.2 million depending on which design is selected.

”The school project is the biggest need for the town,” Selectman James Dwyer said at the State of the Town meeting, adding that work on the community center will not begin until the school is “substantially complete.” However, a community center building committee could be formed as soon as 2021, he said. There has been talk of forming a “Friends of…” group to solicit private donations for one or both campus projects, but this hasn’t yet moved beyond the discussion phase.

There will be two community workshops on the project on Thursday, November 1 at 8 a.m. and 7 p.m. in the Reed Gym. Officials have until November 17 to nail down a final bonding amount for the December 1 and December 3 votes. If approved, architects will require about 12 months to complete detailed drawings before the start of construction, which is expected to take up to three years in two phases.

Category: community center*, government, school project*, schools 1 Comment

School group to tackle final project cost cuts this week

October 15, 2018

The School Building Committee plans to finish trimming the school project to get it under budget this week as it also awaits final information about potential savings on things like temporary classrooms and site work.

The current estimate for construction is $84.98 million, but the construction portion of the budget approved by residents in June is $76.01 million, meaning a total of almost $10 million needs to be cut or found from some other source. In its first two “value engineering” meetings, the SBC approved net reductions of just over $900,000.

The SBC meets on Wednesday, Oct. 17 at 7 p.m. in the Hartwell multipurpose room in a week full of meetings on the school project, including a multi-board meeting on Thursday, Oct. 18. On Tuesday, the Finance Committee will meet to discuss cash flow estimates and bond strategies, solar arrays for the school using capital expenditures vs. a power purchase agreement for the school’s solar array, and the use of debt stabilization funds.

At the October 10 SBC meeting, John Snell, chair of the Green Energy Committee, outlined a combination of construction incentives and energy credits for using green energy sources that could save $400,000–$1 million in the first year, with credits of $208,000–$444,000 annually over 20 years ($4.1 million to $8.9 million total).

The SBC last week also approved several more cost reductions from a list of “value engineering” items provided by architects. The cuts approved in two meetings thus far total $1.05 million:

  • Reseeding rather than sodding playing fields — $141,836
  • Not replacing some existing bookshelves, cabinets, interior doors and markerboards (5 items total) — $511,440
  • Changing floor materials in the learning/dining commons and toilet rooms from porcelain and ceramic to linoleum and epoxy, respectively — $239,514
  • Eliminating a sun shade/canopy and PV array for the new Reed gym link — $68,245
  • Electrical and plumbing items — $90,000

However, the SBC also approved an additional expenditure of $150,000 for a slightly redesigned learning commons/media center/third grade wing, so the net savings thus far are $901,035.

Still undetermined as far as exact dollar amounts are potential savings on temporary classrooms that were budgeted at $3.68 million, photovoltaic direct costs budgeted at $3 million, auditorium work (some of which might be paid for with other funds since that space is also used for Town Meetings), and some portion of the site work (roads and paths, curbs, drainage, landscaping, etc.). A total of $4.98 million could be cut if the only site work done is code-mandated work and repairs after construction.

Finding affordable temporary classrooms (which come with big expenses in addition to their leasing and moving costs) is difficult. “Locally there’s high demand. We have a lot of schools in the area whose enrollment is bursting,” Superintendent of Schools Becky McFall said. School officials even looked at the possibility of busing Lincoln School children to the existing modular classrooms at Hanscom to save on the cost of moving and installing modular classrooms on Ballfield Road, but then every Lincoln School parent would need a pass to get onto the Air Force base, and Hanscom probably has plans for the modular classroom site anyway.

Now that it’s combed through the value-engineering list for items with relatively low dollar values, the SBC will have to discuss cutting some of the bigger-ticket line items. These include:

  • Eliminating all work in the auditorium except code upgrades, sprinklers and HVAC — $1.59 million
  • Eliminating the media center wing and making the learning/dining commons space also accommodate the media center — $1.26 million
  • Eliminating the link to the Reed gym — $1.17 million
  • Keeping preK in the main Hartwell building — $1.01 million
  • Eliminating the third-grade hub space — $210,000

Though not a true savings, officials could also move the $1.06 million cost for furniture and equipment out of the construction budget and into the school’s operating budget.

Category: school project*, schools Leave a Comment

School officials begin cutting items from school project

October 4, 2018

The School Building Committee on Wednesday started the process of changing and removing elements of the school project to meet a voter-mandated budget, making a handful of adjustments from a list provided by SMMA Architects that totaled just over $1.4 million. But the group has more work to do to reach the target total reduction of $8.97 million.

A week ago, the SBC was presented with two independent cost estimates of $102 million and $109 million for the project. Since then, architects and Daedalus, the owner’s project manager, took a closer look at those figures to try to reconcile them. The lower estimate rose while the higher one fell, and the resulting higher figure (the one that the SBC must use for planning) is $104.28 million.

Over the next two weeks, the SBC will continue the “value engineering” process of voting on items to cut that add up to $8.97 million. That figure represents the difference between the $76.01 million construction portion of the total $93.9 million budget approved at a Special Town Meeting in June and the latest construction cost estimate of $84.98 million.

The full project budget also includes non-construction “soft costs”—fees, contingencies, escalation percentages, furniture, technology, permitting, etc. Since June, the estimate for those soft costs has also risen from $17.9 million to $19.3 million.

The areas where cost estimates rose the most compared to June were site work, which went up by $5.22 million, and temporary modular classrooms, which rose by $2.94 million. Before the June vote, the site work plans were more incomplete than the rest of the project and it turns out the required work is slightly more extensive and costly than expected. The earlier estimates had also assumed that some space on the Hartwell side of campus could be sued as temporary “swing space” during construction, but since the spring, it’s become clear that the pods can’t be used for this because they are fully occupied and would also require costly code upgrades to be used as regular classrooms.

The value engineering list includes line items of possible cuts but also a few additions. The SBC on Wednesday approved one of those additions—$150,000 for a tweak to the layout of the learning commons.media center portion of the building that members already approved in principle at their previous meeting.

Some of the biggest dollar items on the value engineering list are program changes, such as eliminating all work to the auditorium except HVAC, sprinklers and fire alarms ($1.59 million); eliminating the media center wing and putting that function in the learning commons area ($1.26 million); eliminating the link between the Reed gym and the main building ($1.17 million); and keeping preK in the main Hartwell building rather than adding it to the renovated building ($1.01 million).

School officials are understandably resistant to these sorts of reductions. “We hate to see programs cut before other things,” said Superintendent of Schools Becky McFall. As for the idea of not building a link between the school and Reed gym, middle school principal Sharon Hobbs was more emphatic, saying it’s “unacceptable” to keep the two buildings detached from each other for safety reasons.

A covered walkway was actually in the initial plan when the gym was built in 1970, but ironically, “it was value-engineered out,” said Buck Creel, Lincoln Public Schools’ administrator for business and finance.

Other ideas floated

Several other cost-cutting ideas were floated as well, but officials need more information before deciding if they are feasible. For example, if the town is able to buy the modular classrooms now being used at Hanscom on favorable terms, it could save up to $1.7 million. Another possibility is reducing or eliminating the direct cost for the photovoltaic system, which would save up to $3 million. That would require amending the town’s solar bylaw to allow selling excess electricity to the grid and working out a favorable contract with the PV vendor.

Yet another possibility is moving the cost of furniture and equipment from the construction budget into the school’s operating budget. This could save $1.06 million on the project, but that money would still have to be appropriated as part of the annual budget process.

Also at the SBC meeting, Town Manager Tim Higgins reported on preliminary research by officials on possible supplementary funding sources for the school project. These include:

  • The Community Preservation Act, which might be applicable to recreational items in the project such as playgrounds
  • Chapter 90 state roadway funds and the Complete Streets state grant program, which might be tapped for Ballfield Road and/or walkway improvements
  • A town fund that receives annual fees paid by cable TV companies, which may be applicable for work in the Brooks auditorium, where televised Town Meetings are held
  • Grants to help pay for photovoltaic (PV) solar panel installations on or near the school

Officials are gathering more information on all of these ideas, but meanwhile, the clock is ticking. The SBC is due to finalize the cost-cutting process on October 17, which will be followed the next day by a multiboard meeting; the annual State of the Town meeting on October 20; a second multiboard meeting/community forum on November 15; and bonding votes by residents at a Special Town Meeting and the polls on December 1 and 3, respectively.

Category: government, school project*, schools Leave a Comment

Latest cost estimates for school project are well over budget

September 26, 2018

Town officials were chagrined Wednesday night to learn that preliminary cost estimates for the Lincoln School project are substantially higher than the $93.9 million budget approved by residents at a Special Town Meeting in June.

At its meeting Wednesday evening, the School Building Committee (SBC) and others heard the two independent estimates for the project—one at $102 million and one at $109 million—in shocked silence. Those numbers are 8.6 percent and 16 percent higher than the original figure, respectively.

On Friday, architects and representatives from Daedalus, the owner’s project manager representing the town, will have an all-day meeting to go over the cost estimating figures in detail and try to reconcile the two estimates by making sure they used the same set of assumptions as to scope, quantities and costs of materials, etc.

“We need to understand why” both figures are significantly higher than the earlier estimate, said Delwyn Williamson, director of cost estimating at Daedalus.

The gross square footage of the project has changed slightly in design tweaks since June, but square footage “is not really making a difference at this point,” Williamson said. One of the contributing factors for the increase may be in the cost of modular classrooms, because early proposals incorrectly assumed that the Hartwell pods could be used for some of the swing space during the two phases of construction, she said. The cost of reusing the modular classrooms from the recent Hanscom projects is also higher than anticipated, but it’s still unclear exactly how much these issues affected the estimates.

Between this Friday and the next SBC meeting on October 3, SMMA will come up with a list of “value engineering” items for the SBC to look at as they consider what aspects of the project to change or remove in order to meet the mandated budget.

“We have a very high level of sensitivity to the community’s need to have that price as low as possible while still preserving the program,” said SBC member Kim Bodnar.

On a hopeful note, Buck Creel, the Lincoln Public Schools administrator for business and finance, noted that the initial estimate for the 2012 project came in at more than $60 million, but the SBC was able to get that amount down to $49 million (although the project eventually failed to get the necessary two-thirds majority at Town Meeting). Part of that reduction came about when the SBC elected not to relocate preK from the Hartwell building to the main school—a move that is also in the current plan, at least for now.

More meetings coming up

The SBC is scheduled to approve a final cost figure on October 17. The group may add another meeting on October 10. There will be a multiboard meeting on October 18 (two days before the annual State of the Town meeting) to gather questions from other town boards, and a second multiboard meeting/community forum on November 15.

A two-thirds majority is required at a Special Town Meeting on December 1 to approve bonding for the project. There will also be a December 3 town-wide ballot that must win a simple majority for the project to advance.

The $93.9 million Option L3 was the mid-priced choice among the three options presented to voters in June. In the final vote, 74 percent of residents voted to move ahead with Option L3, compared to 17 percent for Option C ($94.3 million) and 9 percent for Option L2 ($83 million).

Category: government, school project*, schools 1 Comment

Architects show latest school plans

September 6, 2018

The school floor plan as of September 5 (click to enlarge).

Residents at two workshops on Wednesday saw the latest drawings of the Lincoln School project showing what SMMA principal architect architect Alex Pitkin called “reinvention of the heart of the building” as well as campus circulation and construction phasing.

The middle of the refurbished building includes a central office area and entrance with an “airlock” for both security and climate control. Nearby are offices for the school psychologist, social worker and some special education staff, as well as two large common areas to minimize walking time for students. The media center has been moved to the west side of the building (away from the driveway) since the last presentation two weeks ago.


September 5 workshop presentation:

  • Overall floor plan – pg. 11
  • Entrances – pg. 21
  • Bus and car circulation and dropoffs – pgs. 22-25
  • Pedestrian and bike circulation – pgs. 26-27
  • Sustainable design features – pgs. 35-41
  • Construction phasing – pgs. 44-46

The central area “is a focal point for the building that makes a statement,” said Superintendent of Schools Becky McFall.

There will be a preK entrance at the southwest end of the building and a community entrance at the northeast end to give access to the auditorium and Brooks gyn, which will be connected to the main building. A learning commons for all nine grades replaces the current story room and the seldom used stage area of the Smith gym. Next to it is the dining commons and kitchen.

The new media center will be smaller than what exists today. The current space “is nice, but not ideal for instruction and not well organized for how library/media arts centers are used today.” We don’t efficiently utilize our space right now,” McFall said. Although there will be some “weeding” of the book collection, “we hold tangible paper books in very high value, especially for young kids,” she added.

Pitkin also pointed out the grade-level hubs with movable walls, which “require teachers to have really conscious thought and decision-making about what gets taught where and by whom (movable walls) and which kids are with which teachers where… as opposed to teaching in a one-size-fits-all approach,” McFall said. At the new Hanscom Middle School, which has hubs of this type, “they have made amazing progress in that regard in the last two years, and we still have room to grow in that area.”

Environmentally sustainable features include net zero energy use with all-electric heat as well as photovoltaic arrays on rooftops and over the Brooks parking area, a 30 percent reduction in indoor potable water use, sustainable construction materials, and recycling 75–90 percent of the construction waste.

“The entire building on this campus is going to be re-skinned” with new triple-paned windows and insulation, Pitkin said.

Construction will occur in two phases spanning three years. The auditorium and Smith gym will each be out of commission during one of the 18-month phases. Assuming all goes as planned, 28 modular classrooms plus storage trailers will be installed on the central ballfield in summer 2019.

The schematic designs should take another few weeks, after which teams of cost estimators will come up with firm budget figures to present to the School Building Committee in late September or early October, Pitkin said. The estimates presented at the June 9 Special Town Meeting, where residents selected option L3, was $94 million. 

Category: school project*, schools Leave a Comment

School Building Committee workshops on Wednesday

September 4, 2018

The School Building Committee will hold a pair of identical community workshops on Wednesday, Sept. 5 from 8–10 a.m. and 7–9 p.m. in Reed Gym to recap its work over the summer since the Special Town Meeting vote on June 9. Topics will include:

  • Floor plans – Where are the grades located? How are the hubs and the commons laid out? Where is the new kitchen?
  • Site plan – Traffic flow, pedestrian paths, bike paths, parking.
  • Sustainability – What needs to be done to try to reach our goal of a net zero building?
  • Phasing – Where will students go during renovation?
  • Next steps – What is the SBC working on over the next couple of months?

Topics of future meetings this fall before the December 1 Special Town Meeting to vote on financing the project:

  • September 26 — Review preliminary cost estimates
  • October 3 — Review reconciled cost estimates and value engineering items
  • October 17 — Approve final cost

For more information and a full schedule, see the SBC website or watch videos of past meetings.

Category: school project*, schools Leave a Comment

Schedules proposed for school, community center projects

July 23, 2018

The current school campus showing when various sections were built.

School and community center planners have proposed schedules for further community input and eventual start dates for their respective projects.

Daedalus Projects Inc., the owner’s project manager for the school project, presented a schedule to the School Building Committee earlier this month calling for three community forums from August to October as well as six committee charrettes on various aspects of the school design.

Charrettes on hubs and commons and on building envelope and sustainability took place on June 27 and July 11, respectively. The next session on Wednesday, July 25 at 7 p.n. in the Hartwell multipurpose room will focus on building exteriors and site circulation. Other charrette dates and topics:

  • Systems and photovoltaic panels – August 8
  • Interior spaces and security – August 22
  • Schematic design pricing set – September 5
  • Cost review: September 27

The final cost estimate is due on October 1. Residents must vote on a dollar amount to borrow for the project at a Special Town Meeting on December 1, 2018 (with a two-thirds majority required for passage) and at the ballot box on December 3.

Assuming the project is approved, construction documents and bidding will take place next, with modular classrooms installed in spring and summer 2019, and actual construction running from November 2019 to November 2023.

Community center plan

The Community Center Planning and Preliminary Design Committee submitted its final report outlining two possible design directions on July 19. A survey of residents who attended the June 9 Special Town Meeting showed that voters were almost evenly split on which of the two they preferred.

In their report to the Board of Selectmen, the CCPPDC recommended creating a community center building committee in late 2020. That group would approve a budget for schematic design (currently estimated at $300,000), hire an architect and owner’s project manager, and prepare for a Town Meeting vote on the building site and budget in March 2021.

The town will not have the borrowing or campus space capacity to begin the community center until after the school project is nearly complete. The CCPPDC therefore recommended holding a bonding vote on March 2022 and starting construction in March 2023.

Category: community center*, school project*, schools, seniors Leave a Comment

School option L3 wins the day

June 10, 2018

School option L3 (click to enlarge)

After almost a year of meetings, community forums, architectural work, and spirited debate, Lincoln residents voted to move forward with school concept L3 at a Special Town Meeting on June 9.

Consulting architects SMMA will now produce a schematic design with detailed specifications and an updated cost estimate. The current estimate for Option L3 is $93.9 million, including solar panels and other “net zero” energy use features. A two-thirds majority is required at a Special Town Meeting on December 1 to approve bonding for the project. There will also be a December 3 town-wide ballot that must win a simple majority for the project to advance.

On the first vote, which was conducted using paper ballots and voting machines (a first for a Town Meeting), 632 voters in the Brooks Auditorium and nearby gym weeded down the initial five options to three, with Option L3 gaining a majority already:

Number of votesPercentage
Option R274.3%
Option L1101.6%
Option L28513.4%
Option L335456.0%
Option C15625.7%

Option L3 won a substantial majority in the second round of voting:

  • Option L3 – 74%
  • Option C – 17%
  • Option L2 – 9%

Before turning to the school issue, the Community Center Preliminary Planning and Design Committee presented two possible design ideas for a community center on the Hartwell side of campus and asked residents to complete survey forms on which they preferred. That feedback will be part of the group’s final report to the Board of Selectmen in coming weeks.

The meeting opened with presentations about the five school options and their costs, the tax impacts of borrowing varying amounts, the conditions and repair work needed at the school, and a history of school project planning and construction since 1994, as well as recommendations from the Board of Selectmen, Capital Planning Committee, and Finance Committee (see links below).


Background:

  • A roundup of past Lincoln Squirrel stories and letters to the editor on the school project (updated June 10, 2018)

Town Meeting presentations:

  • Full slide deck
  • Plans and views of the two Community Center options
  • School project history
  • Repairs and code work needed on the school
  • The five school options
  • Borrowing and tax implications plus Finance Committee recommendations

The two community center options (click to enlarge)

Over the past year, the School Building Committee looked at 39 different school options before settling on five to present for the June 9 vote. A sixth option was rejected earlier as being beyond the town’s normal borrowing limit.

Much of the discussion before the votes centered on the educational benefits of hub spaces that would allow teachers to work with student of different sizes and more easily collaborate on teaching within a grade, vs. whether such spaces were worth the added cost.

Dozens of residents stood in line at microphones to ask questions and make a case for their choices before the votes. A sampling of those remarks:

  • “I’m a huge proponent of Options L3 and C… but L3 is probably a compromise,” said Jen Holleran, member of a Lincoln educators group.
  • Option L3 would put Lincoln “in the middle of the pack for residential tax rate,” said Ginger Reiner. “What we are experiencing as a giant leap in taxes is just recalibrating to bring us more in line with our neighbors. We’ve enjoyed lower than average taxes by essentially borrowing against our future selves; we’ve artificially suppressed our taxes and it’s time to pay that debt… Option L3 is the perfect intersection of the town’s values.”
  • “Our kids are doing all right,” said Carolyn Montie, noting the top-tier colleges that many Lincoln School graduates have attended. “All options are viable… but putting those resources to direct services to students would result in a better outcome.”
  • “Every dollar put into the school made real estate prices rise by $1.50” compared to similar towns that didn’t do a major school project, said Ben Shiller, assistant professor of economics at Brandeis University, citing academic research. “The selfish decision is actually to choose one of the more expensive options.”
  • Lincoln’s master plan doesn’t mention an upgraded school but does call for continued investment in affordable housing, open space and conservation, and economic development, said Sharon Antia. “Where will we find the dollars for our stated priorities?”
  • Children today “have information at their fingertips—they don’t need to cram it all into their heads” in a traditional classroom setting, said D.J. Mitchell. “We need to [develop] collaborators, tinkerers, and problem solvers. Sometimes this requires larger spaces, multi-age groupings, teachers working across disciplines, quiet reflection and loud collaboration… we need to transform educational spaces for the 21st
    century.”
  • “We have a responsibility to honor the historical legacy of the Smith School, which was groundbreaking in its day,” said Christopher Boit. Option L2 “honors our commitment to net zero as well as a full kitchen and [the option of] collaboration at mealtimes… the difference in my education was not the buildings, it was the teachers.”
  • The hub spaces in Options L3 and C mean that children taken aside for individual or small-group instruction for any reason “are not stigmatized by being pulled into hallways,” said Cathy Bitter.
  • “We’re going to end up taking people out of this community because this is going to impact their taxes a lot,” said Daniela Caride. “In Lincoln, you go anywhere and you see three generations of people living here. [Other area towns] are generally bedroom communities. Do we want to be this kind of community? I’m still looking for an option here. We should be mindful of our neighbors who may get into trouble with all this cost.”
  • The tax increase from L2 to either L3 or C “sounds like a pretty good bargain,” said Cheryl Gray.
  • The increase between the higher-end options which is in the vicinity of $200-300 annually “is just one less trip to Donelan’s,” said Chris Gill.
  • “Some people are concerned that the price is still not optimal for what we’re getting, so I hope do some serious value engineering” between now and December,” said Steve Massaquoi.
  • “Given the total dollar amounts we’re talking about, I’m not that concerned” about the relative difference in tax hikes between the top two or three options, said Allen Vander Meulen. “But which of the plans do the teachers prefer?”
  • At the most basic level, consistent classroom temperature and lighting are the top priorities for teachers, Superintendent of Schools Becky McFall said in answer to Vander Meulen’s question. But since the new Hanscom Middle School opened, “they’re seeing the collaboration possibilities… the flexible grouping of students and targeted instruction… for either more intervention or more challenges.”
  • The presence of hubs in a school “affects our ability to attract good teachers big-time,” said Bob Shudy. Without hubs, many of the best young teachers “wouldn’t even consider” applying to work at the Lincoln School.
  • Option L2 “contains the reasonable minimum for facilities and teachers. I find the notion of adding hubs or flex spaces to be speculative,” said Adam Greenberg. “Education is changing much more rapidly than any snapshot you choose to pick today.”
  • Saying she hoped to persuade fans of both Option L2 and C to agree on L3, Lis Herbert said that L2’s concept of having only single flex spaces for Smith and Brooks is “deficient and doesn’t rise to the occasion” but that Option C reflects “a uniquely American desire for shiny, efficient new things. We often forget about what we have and what we can adapt to suit our needs… we literally pull up stakes and go west.”
  • “A difference of $10 million between L2 and L3 is significant,” said Diana Abrashkin. “There’s so much that could be done with $10 million in terms of teacher salaries, or more amenities in the actual buildings. The difference is the teachers, not the shape of the classrooms.”
  • Option L3 has a better distribution of hub spaces, while Option C has “a perfectly good gym moved from present location,” said Graham Atkinson.

Category: community center*, government, news, school project*, schools 3 Comments

Letter to the editor: Mostue supports option L3

June 7, 2018

To the editor:

First, I applaud all the individuals who have worked so hard on the most difficult Lincoln issue I have witnessed in my 26 years in town. Thank you.

In almost every project during my 40 years of architectural practice, I have had to help clients make the best possible decisions in allocating limited resources across greater needs. After careful consideration, I plan to support SBC Option L3 based on several beliefs. I call them beliefs because many of you will disagree with at least a few:

  • Some action needs to be taken.
  • A comprehensive approach is better than a piecemeal approach for many reasons stated in eloquent detail by Gary Taylor’s May 31 post on LincolnTalk (Lincoln Digest, Vol 64, Issue 31) and others. [Editor’s note: Taylor’s post has also been published here in the Lincoln Squirrel.] 
  • Preserving existing structures, site infrastructures, and the embodied energy they collectively represent is the most environmentally sustainable decision that can be made in planning for construction.
  • Sustainability considerations should not stop with preservation. (Aside: The SBC must early and clearly establish the community’s priority focus among the types of sustainability—energy performance vs. low carbon footprint vs. health vs. cash savings. Strategies for each can conflict and all may not be economically achievable within a single project. Hard choices will inevitably have to be made. Clear priorities will help to make them.)
  • Preserving history has value.
  • Preserving aged trees has value.
  • Giving clear direction to the design team will now allow them to focus their creativity and improve the selected design.
  • L3 achieves a number of educational objectives.
  • L3 is not significantly less compact than alternatives.
  • L3 has the potential to be tightened in ways that will reduce area.
  • L3 lends itself better to potentially reducing construction costs.
  • L3 preserves and could actually enhance the existing attractive campus feel.
  • L3 exercises a modicum of fiscal prudence—leaving some allowance for energy conservation upgrades, prudent maintenance, future support for school budgets and teachers, a community center, the fear of project cost overruns or unforeseen town expenditures, and the like.
  • L3 has the best chance to win at the polls.

In a democracy, not every individual gets his/her cake and eats it, too. But I think it is now time that action must be taken, and the most reasonable path seems to me to be L3.

Sincerely,

Brooks Mostue
3 Lexington Rd., Lincoln

Category: letters to the editor, school project*, schools Leave a Comment

Letter to the editor: a brief history of the school project

June 6, 2018

To the editor:

We are approaching a critical vote on the future of Lincoln’s school facilities.  There is a long history of the various deliberations that have gone before. It is often difficult for people to become fully informed of what has gone before. As someone who has been involved for a very long time, I offer this Cliff Notes version of how we have come to the decision we face on June 9. Please become informed and come to vote.

Recent discussions on LincolnTalk and letters to the Squirrel pose numerous questions suggesting that a significant number of the commenters may be unfamiliar with the lengthy saga of efforts to address deficiencies in Lincoln’s K-8 school facilities. Many of the questions asked and the expert review requests made have been raised and addressed in in the past, but the complete record of the proceedings to date is voluminous, so it’s perhaps unreasonable simply to direct inquisitive citizens to plow through all of the documents on the subject available on the school and town websites. It may therefore be helpful to provide a short history of these efforts. For those of you interested in delving more deeply into the history, click here.

Let me say at the outset that I do not have a unique perspective on the school project proceedings, but I do have a lengthy one. I was the Selectmen’s representative on the original SBC, and eventually became co-chairman. Along with a few others, I represented Lincoln’s interests before the MSBA [Massachusetts School Building Authority]. Since then, I have served on every committee that has evaluated the options for addressing needs at the Lincoln Schools, and now am the Planning Board liaison to the SBC. 

The story begins with the so-called 1994 renovation project. In the early 1990s, the town began considering renovation of the school facilities. Architects were retained to evaluate the physical plant and to come up with an improvement plan. Their original proposal would have remedied building deficiencies, added kitchen and dining facilities common in other schools, and connected the Smith, Brooks, and Reed Gym buildings. The cost was estimated at just above $22 million.

Lincoln’s leadership, faced at the time with also building a new public safety building, sent the architects back to the drawing board to develop three options at a range of price points all significantly below the initial offering. These options were presented at Town Meeting, and the middle option, at less than $12 million, was selected.

This project obviously did not provide central dining room and kitchen or the link to Reed. It also did not address some of the glaring deficiencies identified by the architects, such as the below-grade heating system boilers in the Smith building that periodically flooded (and have on occasion been under more than 50 inches of water). Many people have interpreted the 1994 project as a complete rehabilitation of the facility, but this is simply not the case. Portions of the building needing attention remained untouched.

Because the 1994 project left a lot of needs unmet, it wasn’t long before the schools were seeking annual capital infusions to ameliorate them. In 2003, Lincoln’s Capital Planning Committee concluded that a piecemeal approach might not be the best way to deal with facilities issues and asked the School Committee to take a more comprehensive approach.

This led to studies by two architectural firms in 2004 and 2007 which identified significant facility needs. The latter of these, by [current consulting school architect] SMMA, developed a range of options running from simple repairs at $35 million to a significant rebuild at $65 million. By this time, legislation establishing the MSBA was passed, and the possibility of state funding arose. Lincoln took the opportunity to make an application to participate in the process.

Lincoln was on of 21 schools selected from among 238 applications to start the MSBA feasibility study process.  This involved a rigorous review of the condition of Lincoln’s facilities and how they matched up with both the school’s educational program and MSBA standards. This turned out to be a long and arduous process because Lincoln’s physical plant is so far beyond the norm for peer K-8 facilities in terms of size and number of classrooms, having two gyms and a large auditorium complex (needed for annual TM)—unusual in K-8 schools.

The MSBA staff questioned everything in terms of educational and facility needs, and we pushed them way beyond their normal boundaries in terms of time and effort, taking twice as long as normally allowed. Ultimately we reached an accommodation and got very favorable reimbursement rate—44 percent of qualifying facilities and 42 percent of the overall cost, a better rate than most projects in surrounding towns. 

The Preliminary Design Plan approved by MSBA had an estimated cost of $61.3 million. Scope reduction and value engineering in the development of the subsequent schematic design process cut the cost from $61.3 million to $49.9 million. With the MSBA contribution of $20.9 million, the cost to Lincoln taxpayers would have been $29 million.

Because of concerns about the cost of the project, Lincoln’s Finance and Capital Planning Committees commissioned an independent study of potential repair approaches. The resulting Maguire Report confirmed that there was no cheap way out of the problems on the school campus. It concluded that the best approach to repairs needed within 10 years would cost $33 million (in 2013 dollars) and yield little educational benefit.

In the end, the effort went for naught. Town Meeting in 2012 failed to muster the required a two-thirds vote to bond the MSBA-approved project. Lincoln applied three more times, but the MSBA bureaucracy, once burned and with many other applicants, turned Lincoln down. Lincoln is not barred from participation, but our chances of being admitted again are slim, as the MSBA can legitimately question whether or not Lincoln can effectively organize support. Town Meeting in 2017 thus decided to go it alone without MSBA participation.

So here we are, years later, facing the same basic problems, but with no MSBA support. Again, two major capital projects are looming, but we seem wisely to have agreed to sequence them. The question before residents is, how much can we responsibly spend on the schools? People’s opinions can vary, but there is no question that, at minimum, there will need to be a major investment.

MSBA evaluators, trying to pinch every penny, agreed to this fundamental need. Four different architectural firms have also agreed. All these professionals and Lincoln’s own Capital Planning Committee have favored a single, comprehensive project over serial, remedial repairs. The current Finance Committee has recently added its weight in favor of a comprehensive approach.

With years of cost escalation in a booming construction market, essential repairs will cost on the order of $49 million. The only question remaining for Lincoln residents is how much we are willing to invest in the educational enhancements that our own educators, and education professionals elsewhere, believe would benefit Lincoln’s school community, both students and teachers. 

Sincerely,

Gary Taylor
2 Beaver Pond Rd.

Category: government, school project*, schools Leave a Comment

  • « Go to Previous Page
  • Page 1
  • Page 2
  • Page 3
  • Page 4
  • Page 5
  • Page 6
  • Interim pages omitted …
  • Page 14
  • Go to Next Page »

Primary Sidebar

Upcoming Events

May 31
8:00 pm - 11:00 pm

Club Codman

Jun 14
9:00 am - 2:00 pm

Hazardous waste dropoff

Jun 14
11:00 am - 3:00 pm

250th anniversary Feast & Faire

Jun 14
4:30 pm - 7:00 pm

Codman Campout and Chili Night

View Calendar

Recent Posts

  • Legal notice: Select Board public hearing (Goose Pond) May 14, 2025
  • News acorns May 13, 2025
  • Wentworth named acting chief of police May 13, 2025
  • Police Chief Sean Kennedy arrested on domestic violence charges May 12, 2025
  • Police log for April 26 – May 8, 2025 May 11, 2025

Squirrel Archives

Categories

Secondary Sidebar

Search the Squirrel:

Privacy policy

© Copyright 2025 The Lincoln Squirrel · All Rights Reserved.